Interested in a career where you can make a difference?

Click here to view our open positions.

Lubbock Northwest Wastewater Treatment Plant Construction

CLIENT NAME

City of Lubbock

LOCATION

Lubbock, Texas
United States

PRACTICE AREA

Construction Management

SERVICES INCLUDED

Design

Construction Management & Administration

Full-time RPR

Contractor Coordination

Project Gallery

Images
No items found.

The City of Lubbock contracted with Plummer for a new 3 million gallons per day wastewater treatment plant.  The project included a raw water pump station, pretreatment units, biological reactors, membranes, UV treatment, buildings, site work, and paving.  We supported the City during the construction phase with full-service construction management and resident representative services. The project consisted of multiple structures, underground utilities, odor control, storage tank, paving, electrical, SCADA, and site work. The project design included a first-in-the-US combination of surface aerator aeration basins paired with a membrane bioreactor system and is the largest flat sheet membrane bioreactor facility in Texas.

Similar PROJECTS

Lubbock 8 Million Gallon Storage Tank

Plummer is providing third party construction management and resident project representative services on the construction of a new 8 MG water storage tank.

Round Rock Brushy Creek Wastewater Treatment Plant Expansion

Plummer is serving as Construction Manager and Resident Project Representative for the 10 MGD, $107M expansion.

No items found.

Work With Us

We design solutions to the world's greatest challenges. We're ready to take on any problems you may run into.