The City of Lubbock contracted with Plummer for a new 3 million gallons per day wastewater treatment plant.  The project included a raw water pump station, pretreatment units, biological reactors, membranes, UV treatment, buildings, site work, and paving.  We supported the City during the construction phase with full-service construction management and resident representative services. The project consisted of multiple structures, underground utilities, odor control, storage tank, paving, electrical, SCADA, and site work. The project design included a first-in-the-US combination of surface aerator aeration basins paired with a membrane bioreactor system and is the largest flat sheet membrane bioreactor facility in Texas.

Similar PROJECTS

New Braunfels Utilities Avery Park Pipeline Construction

The project includes the installation of approximately 25,000 linear feet of 30-inch water main, 2,800 linear feet of 16-inch water main and appurtenances.

Lubbock 8 Million Gallon Storage Tank

Plummer is providing third party construction management and resident project representative services on the construction of a new 8 MG water storage tank.